December 2: Kyle did lots of house errands while Rusty kept working on showers, got tons of things order for house using the cyber Monday deals.
December 3: Kyle continued to hang plastic on the walls
December 4: cedar posts were delivered, painted all the exterior doors black
December 5: Kyle finished painting the doors black
December 6: Went to Des Moines and picked up more tile for shower and backsplash. , laundry room tile, tried to find a hardwood floor
December 9: Drywall was delivered to the house
December 10: Drywall guys arrived and started on the main floor
December 11: Drywallers continued, Kyle and Rusty worked on attic insulation
December 12:Rusty started on the porch roof trusses, Meredith started painting laundry cabinet
December 13: Rusty continued to work on the porch and got the two cedar poles put in
December 14:Kyle made a big Menards run to get the cedar boards for the deck. Kyle and Levi finished insulation in the garage attic.
December 17: Porch frame began and Kyle and Mitchell finished attic insulation above the hosue.
December 18: All handles put into the exterior doors and deck frame completed and started putting top boards on.
December 19: Continued work on the deck, Rusty put in the first garage door, Mudders and Tapers came to work on drywall, I paintined laundry cabinet
December 20 Deck finished!
December 23/24: Mudders and tapers were there and kept things rolling.
December 26: Drywall mudding and taping continued, Kyle did Menards run
December 27: Finished up sanding drywall, Kyle worked on electrical hookups
December 30: Drywall walls and ceiling sprayed texture and ceilings painted and finished!!
December 31: I prepped the house for painting, put in new lightbulbs,started painting the navy stairs wall and started painting Wyatt’s room and walls for stenciling.
January is going to be HUGE and I am ALL for it!! Absolutely can not wait! We are getting so close.